TCN Restores Power on Benin/Omotosho 330kv Tramsnission Line
By Core Reporters
Benin (Core Reporters) The Transmission Company of Nigeria, (TCN) has restored power on the Benin-Omotosho 330kV Transmission Line. The power was restored at 7:05 pm on Thursday, July 2, 2026.
The restoration followed an outage on the line on June 25, 2026, caused by detachment of conductors. TCN engineers have since worked to restring and complete maintenance on the affected sections of the transmission line.
With the line now back in service, the Benin Electricity Distribution Company (BEDC), Eko Electricity Distribution Plc (Eko DisCo) and Ikeja Electric will be able to off-take more power for supply to their customers in their franchise areas.
Core Reporters report that, TCN apologises for the inconvenience caused by the outage and appreciates the understanding and cooperation of all affected during the period.